Re: Manufacturing advice needed - materials of measured units being consumed partially
Re: Manufacturing advice needed - materials of measured units being consumed partially
Re: Manufacturing advice needed - materials of measured units being consumed partially
by
Data Dance s.r.o., Radovan Skolnik
Hello, thank you for all the answers.I guess I have to test this thoroughly. My worry is generally this: let's say I have 2 lots/rolls each with 50m raw cable remaining. I need to produce 100m final cable. I think the system would consider I have enough of raw cable for this. Because that would work for certain scenarios. Imagine you need 100kg of something to prdouce something else. If you have 2 lots each with 50kg you're good to go - you just combine 50kg from each. Similarily if it was pieces. All these can be joined / added. I am talking about scenario where partial residual amounts cannot be added together to create a larger piece / amount. Hope I am making myself clear. Best regards Radovan On štvrtok 27. januára 2022 0:17:23 CET James Dominy wrote: > Hello Radovan, > I would track your rolls of cable using Lots, this way when the order calls > for 25, 50, or 100 m of cable if the lot does not have the qty needed to > produce the ethernet cable it will use the lot that has enough for the > finished product. On Wed, Jan 26, 2022 at 3:57 PM Radovan Skolnik < > radovan@skolnik.info [1] > wrote: Daniel, > thank you for answer. Yes it does make sense. But will it cover scenario > where I have let's say 2 rolls with 50m remaining on each and I want to > produce 100m final cable? Because in such case a completely new roll should > be ordered as I cannot join those 2 50m pieces together... So it comes to a > requirement here that you just do not track the total number of meters > remaining but you need to track each roll individually. Similar example > would be a woodmaker who needs certain sizes of wood for various products > (chair, table, ...) and he procures wood in 3m planks. What is your > opinion? Best regards > Radovan > > On streda 26. januára 2022 21:51:47 CET Daniel Reis wrote: > > I believe you need to use different Units of Measure (UoM). > > In this case, the "Cable" Product is purchased in "Rolls" and used > > in "Meters". > > The "Roll" UoM should be configured to convert to Meters at a rate > > of 1:1000. > > This way you track your cable stock in meters available, and you > > order to your supplier in rolls. > > Dos this make sense? > > Thanks > > Daniel > > > > On 26/01/22 20:37, Radovan Skolnik > > wrote: > > > > Hello, > > sorry for asking stupid questions here but I hope someone can provide some > > wisdom here that I am missing. Let's imagine this scenario: I produce > > Ethernet cables of various lengths - i.e. 25m, 50m, 75m, 100m, ... Each > > such final cable requires 2 connectors and that particular amount of "raw" > > cable. I can only buy raw cable in rolls of 1000m. So when I buy a new > > roll > > and produce one final 50m cable, 950m of raw cable remains. When I produce > > another of 100m length, 850m of raw cable remains. When my remaining raw > > cable on certain roll is 50m I cannot produce 100m final cable and need to > > order another raw cable roll. So the idea is tracking remaining quantity > > of > > somethings (products? lots? ...) that is bought at certain size and is > > being gradually consumed. There can of course be more of these (i.e. I > > have > > bought 3 rolls at the same time). Is there a way on how to model this? > > Manufacturing is not really my domain and looking through code of various > > modules I didn't find anything that would resemble such thing. Thank you > > very much. Best regards > > Radovan Skolnik > > > > > > _______________________________________________ > > Mailing-List: https://odoo-community.org/groups/contributors-15 [2] [1] > > Post to: mailto: contributors@odoo-community.org [3] [2] > > Unsubscribe: https://odoo-community.org/groups?unsubscribe [4] [3] > > > > > > > > -- > > DANIEL > > REIS* > > MANAGING DIRECTOR > > M:* > > +351 919 991 307 > > E:* > > dreis@OpenSourceIntegrators.com [4] > > A:* > > Avenida da República 3000, Estoril Office B, #34 > > > > > > None [5] None [6] None [7] > > > > > > _______________________________________________ > > Mailing-List: https://odoo-community.org/groups/contributors-15 [5] [8] > > Post to: mailto: contributors@odoo-community.org [6] > > Unsubscribe: https://odoo-community.org/groups?unsubscribe [7] [9] > > > > > > > > [1] https://odoo-community.org/groups/contributors-15 [8] > > [2] mailto: contributors@odoo-community.org [9] > > [3] https://odoo-community.org/groups?unsubscribe [10] > > [4] mailto: dreis@OpenSourceIntegrators.com [11] > > [5] https://www.magentointegrators.com/ [12] > > [6] https://www.hadoopintegrators.com/ [13] > > [7] https://www.usaodoo.com/ [14] > > [8] https://odoo-community.org/groups/contributors-15 [15] > > [9] https://odoo-community.org/groups?unsubscribe [16] > > _______________________________________________ > Mailing-List: https://odoo-community.org/groups/contributors-15 [17] > Post to: mailto: contributors@odoo-community.org [18] > Unsubscribe: https://odoo-community.org/groups?unsubscribe [19] > > -- > * James Dominy * > CEO > * Lunel, Inc * > Saratoga Springs, UT > 719-888-9582 > jamesdominy@lunelerp.com [20] > * www.lunel.co [21] > * > > _______________________________________________ > Mailing-List: https://odoo-community.org/groups/contributors-15 [22] > Post to: mailto:contributors@odoo-community.org > Unsubscribe: https://odoo-community.org/groups?unsubscribe [23] > > > > [1] mailto:radovan@skolnik.info > [2] https://odoo-community.org/groups/contributors-15 > [3] mailto:contributors@odoo-community.org > [4] https://odoo-community.org/groups?unsubscribe > [5] https://odoo-community.org/groups/contributors-15 > [6] mailto:contributors@odoo-community.org > [7] https://odoo-community.org/groups?unsubscribe > [8] https://odoo-community.org/groups/contributors-15 > [9] mailto:contributors@odoo-community.org > [10] https://odoo-community.org/groups?unsubscribe > [11] mailto:dreis@OpenSourceIntegrators.com > [12] https://www.magentointegrators.com/ > [13] https://www.hadoopintegrators.com/ > [14] https://www.usaodoo.com/ > [15] https://odoo-community.org/groups/contributors-15 > [16] https://odoo-community.org/groups?unsubscribe > [17] https://odoo-community.org/groups/contributors-15 > [18] mailto:contributors@odoo-community.org > [19] https://odoo-community.org/groups?unsubscribe > [20] mailto:james@lunelerp.com > [21] http://www.lunel.co > [22] https://odoo-community.org/groups/contributors-15 > [23] https://odoo-community.org/groups?unsubscribe
Reference
-
Manufacturing advice needed - materials of measured units being consumed partially
byData Dance s.r.o., Radovan Skolnik-
Re: Manufacturing advice needed - materials of measured units being consumed partially
byMoaHub, Graeme Gellatly -
Re: Manufacturing advice needed - materials of measured units being consumed partially
byData Dance s.r.o., Radovan Skolnik -
Re: Manufacturing advice needed - materials of measured units being consumed partially
byMoaHub, Graeme Gellatly -
Re: Manufacturing advice needed - materials of measured units being consumed partially
byData Dance s.r.o., Radovan Skolnik -
Re: Manufacturing advice needed - materials of measured units being consumed partially
byponkhi403 -
Re: Manufacturing advice needed - materials of measured units being consumed partially
byLuNel, Inc, James Dominy -
Re: Manufacturing advice needed - materials of measured units being consumed partially
byLandis Arnold -
Re: Manufacturing advice needed - materials of measured units being consumed partially
byData Dance s.r.o., Radovan Skolnik -
Re: Manufacturing advice needed - materials of measured units being consumed partially
byClosingAp Open Source Integrators Europe, LDA, Daniel Reis
-